hardware-prd
GitHub用于编写物理硬件产品需求文档(PRD),涵盖BOM至落地成本栈、全球法规认证矩阵、可靠性指标及服务包装要求。适用于新设备规格定义或NPI项目启动,强制明确工具化后的高成本决策点。
触发场景
安装
npx skills add mohitagw15856/pm-claude-skills --skill hardware-prd -g -y
SKILL.md
Frontmatter
{
"name": "hardware-prd",
"description": "Write a PRD for a physical hardware product — target cost (BOM and landed), industrial design constraints, regulatory certifications, reliability targets, serviceability, packaging, and forecast assumptions. Use when asked to write a hardware PRD, spec a new device, define requirements for a physical product, or kick off an NPI program. Produces a complete hardware PRD with a cost stack, cert matrix, reliability spec, and EVT\/DVT\/PVT milestone targets."
}
Hardware PRD Skill
A software PRD can ship wrong and patch later; a hardware PRD is cut into steel and soldered onto boards. This skill writes a PRD that forces the decisions that get expensive after tooling: cost targets with a full stack (not just BOM), certifications named per market, reliability as numbers, and forecast assumptions stated so the supply chain can be sized honestly.
What This Skill Produces
- A complete hardware PRD with numbered, testable requirements (shall-statements)
- A target cost stack: BOM → COGS → landed cost, with margin math
- A regulatory/certification matrix per target market
- Reliability, serviceability, and packaging requirements with acceptance numbers
- Forecast assumptions and the EVT/DVT/PVT milestones the schedule hangs on
Required Inputs
Ask for these if not provided; if the brief is thin, infer sensible values and label each one [assumed — confirm]:
- Product concept and user — what it is, who buys it, key use environment (indoor/outdoor, temp range, drop risk)
- Target retail price and channel — retail vs D2C changes the margin stack
- Target markets — determines the cert list (US, EU, UK, etc.)
- Power source — battery (chemistry, size) vs mains changes safety certs entirely
- Forecast — units for year 1 and lifetime, plus confidence
- Launch window and any hard date (e.g. holiday season)
Cost & Certification Framework
Cost stack — always build all four layers; never let "cost target" mean BOM alone:
| Layer | Contains |
|---|---|
| BOM | Components, PCBA, mechanicals, packaging materials |
| COGS | BOM + assembly/test labour + scrap/yield loss + factory overhead |
| Landed | COGS + freight + duty/tariff (HTS code, country of origin) + insurance |
| Margin check | Landed vs channel price after retailer margin (typ. 30–50% retail) |
Cert matrix — map each market to its certs. Typical starters: FCC Part 15B (unintentional) / 15C (Wi-Fi/BT radio), CE (RED, EMC, LVD), UKCA, safety UL/IEC 62368-1, RoHS/REACH/Prop 65, batteries UN 38.3 + IEC 62133. Flag any radio module choice that lacks modular certification — it adds months.
Reliability targets — state as numbers: MTBF (hours), warranty return rate ceiling (% in 12 months), lifetime (years/cycles), and the abuse cases (1 m drop, IP rating, operating temp range).
Output Format
Hardware PRD: [product]
- Overview & user — problem, user, use environment
- Requirements — numbered shall-statements grouped: functional, industrial design (size/weight/CMF limits), environmental
- Target cost stack — the four-layer table with numbers and margin math
- Regulatory & certification matrix — market × cert × owner × lead time
- Reliability & quality targets — MTBF, return-rate ceiling, abuse cases, ORT expectation
- Serviceability & repair — field-replaceable units, disassembly, spare-parts strategy
- Packaging — retail vs bulk, drop-test spec (e.g. ISTA 3A), dielines owner
- Forecast assumptions — Y1/lifetime units, MOQ implications, ramp shape
- Milestones — EVT/DVT/PVT/MP dates and what each gate must prove
- Open questions & assumptions — everything labelled
[assumed — confirm]
Quality Checks
- Every requirement is testable — a DVT engineer could write a pass/fail test from it
- Cost target includes landed cost and survives the channel-margin math
- Every target market has its certs listed with lead times
- Reliability targets are numbers, not adjectives ("robust" is not a spec)
- Forecast assumptions are explicit enough to size tooling and MOQs against
- Battery products name chemistry and the UN 38.3 / IEC 62133 path
Anti-Patterns
- Do not state a cost target without saying which layer it is — "$40 target" that turns out to be BOM-only kills the margin at landed
- Do not write "certified for global markets" — name each market and each cert
- Do not spec reliability as "high quality" — give MTBF, return-rate ceiling, and abuse cases
- Do not omit serviceability — an unrepairable design is a warranty-cost decision, so make it consciously
- Do not hide forecast uncertainty — tooling cavitation and MOQs are bought against this number
- Do not refuse a thin brief — draft with labelled assumptions and list what must be confirmed before EVT