根据冲刺数据和目标生成结构化的冲刺简报,涵盖目标、理由、工作分组、关键路径、风险及完成定义。适用于编写冲刺摘要、文档化目标或制作团队视角的概览,确保信息清晰易读。

exports/openclaw/sprint-brief/SKILL.md mohitagw15856/pm-claude-skills

Trigger Scenarios

要求撰写冲刺简报 创建冲刺总结 文档化冲刺目标和范围 生成团队面向的冲刺概览

Install

npx skills add mohitagw15856/pm-claude-skills --skill sprint-brief -g -y
More Options

Non-standard path

npx skills add https://github.com/mohitagw15856/pm-claude-skills/tree/main/exports/openclaw/sprint-brief -g -y

Use without installing

npx skills use mohitagw15856/pm-claude-skills@sprint-brief

指定 Agent (Claude Code)

npx skills add mohitagw15856/pm-claude-skills --skill sprint-brief -a claude-code -g -y

安装 repo 全部 skill

npx skills add mohitagw15856/pm-claude-skills --all -g -y

预览 repo 内 skill

npx skills add mohitagw15856/pm-claude-skills --list

SKILL.md

Frontmatter
{
    "name": "sprint-brief",
    "homepage": "https:\/\/mohitagw15856.github.io\/pm-claude-skills\/skill\/sprint-brief.html",
    "metadata": {
        "openclaw": {
            "emoji": "🚚"
        }
    },
    "description": "Generate a structured sprint brief from sprint data and goals. Use when asked to write a sprint brief, create a sprint summary, document sprint goals and scope, or produce a team-facing sprint overview. Produces a scannable brief with sprint goal, rationale, grouped work, critical path, risks, and definition of done."
}

Sprint Brief Skill

Produce a clear, scannable sprint brief that every team member — engineer, designer, PM — can read in under three minutes and understand exactly what we're doing and why.

Required Inputs

Ask the user for these if not provided:

  • Sprint name and number
  • Sprint goal (1-2 sentences — flag if too vague)
  • Ticket list with owners (or a description of the work)
  • Known dependencies or blockers
  • Carry-over items from previous sprint (if any)

Process

  1. Read sprint goal and check it's specific and measurable — flag if it's too vague
  2. Group tickets by theme or feature area
  3. Identify the critical path — which tickets must complete for the sprint goal to be met?
  4. Flag risks: tickets with unclear acceptance criteria, missing designs, unresolved dependencies
  5. Note carry-over items and whether they affect this sprint's goal
  6. Validate — Confirm the sprint goal is achievable given the ticket scope and capacity. If the critical path items alone would fill the sprint, flag it as overloaded.

Output Structure

Sprint [Number] Brief — [Dates]

Sprint Goal: [1-2 sentences — specific and measurable] Why This Sprint Matters: [Connect to quarterly OKR in 2-3 sentences]

What We're Building:

  • [Theme 1]: [tickets and owners]
  • [Theme 2]: [tickets and owners]

Critical Path: [The 2-3 tickets everything else depends on]

Risks to Flag:

  • [Risk 1 + mitigation]
  • [Risk 2 + mitigation]

Carry-over from Last Sprint: [List + impact on current goal]

Definition of Done: [Specific, agreed criteria for sprint success]

Scoring Rubric (0–40)

Score any output of this skill before handing it over; 32+ is ship-quality.

Dimension 0 5 10
Goal scoreability Goal is a task list or a vague direction ("make progress on X") — nobody could score it at sprint end Goal states one outcome but the pass/fail line is fuzzy (no number, date, or observable test) Goal is a single outcome statement with an explicit pass/fail test anyone on the team could apply on the last day
Critical path precision No critical path, or "the important tickets" — reader can't tell which slippage is fatal Critical path tickets are named but without sequencing or the date/trigger at which the goal fails Named tickets in dependency order, with the deadline that kills the goal and a clear fatal-vs-survivable split from the rest of the board
Risk actionability Risks are a worry list — no mitigations, no owners Each risk has a mitigation or an owner, but responses are generic ("monitor closely") Every risk has a concrete mitigation with a ready-by date and a single named owner, and states whether it threatens the goal or just a ticket
Capacity honesty Carry-over listed without impact; board is silently overloaded Carry-over impact on the goal is stated, but the brief doesn't act on it — overload is flagged as a risk and left there Carry-over is costed against capacity and the brief shows the resolution: named scope cuts, a de-scoped goal, or an explicit team-agreed overload acceptance

Quality Checks

  • Sprint goal is specific enough to score pass/fail at the end of the sprint
  • Critical path items are named — not just "the important ones"
  • Every risk has a mitigation or owner (not just "this is a risk")
  • Carry-over items are connected to their impact on this sprint's goal
  • Definition of Done is agreed criteria, not a task list

Anti-Patterns

  • Do not write a sprint goal as a task list — the goal must be a single outcome-focused statement that can be scored pass/fail
  • Do not leave the critical path unnamed — "the important tickets" is not a critical path
  • Do not list risks without a mitigation or owner — a risk without a response is just a worry list
  • Do not ignore carry-over items' impact on this sprint's capacity and goal
  • Do not write a Definition of Done that mixes task completion with outcome criteria — they must be observable and agreed before the sprint starts

Version History

  • 54fad50 Current 2026-07-19 12:34

Same Skill Collection

exports/openclaw/360-feedback-template/SKILL.md
exports/openclaw/401k-plan-decoder/SKILL.md
exports/openclaw/ab-test-planner/SKILL.md
exports/openclaw/ab-test-readout/SKILL.md
exports/openclaw/accessibility-audit/SKILL.md
exports/openclaw/account-plan/SKILL.md
exports/openclaw/acquirer-red-team/SKILL.md
exports/openclaw/ad-copy/SKILL.md
exports/openclaw/aeo-optimizer/SKILL.md
exports/openclaw/agenda-or-cancel/SKILL.md
exports/openclaw/agent-design-review/SKILL.md
exports/openclaw/agent-observability-spec/SKILL.md
exports/openclaw/agent-spec/SKILL.md
exports/openclaw/ai-ethics-review/SKILL.md
exports/openclaw/ai-eval-plan/SKILL.md
exports/openclaw/ai-feature-prd/SKILL.md
exports/openclaw/ai-product-canvas/SKILL.md
exports/openclaw/air-quality/SKILL.md
exports/openclaw/altitude-shifter/SKILL.md
exports/openclaw/ambiguity-resolver/SKILL.md
exports/openclaw/analyst-relations-brief/SKILL.md
exports/openclaw/announcement-card/SKILL.md
exports/openclaw/api-docs-writer/SKILL.md
exports/openclaw/api-test-plan/SKILL.md
exports/openclaw/api-versioning-strategy/SKILL.md
exports/openclaw/apology-letter/SKILL.md
exports/openclaw/architecture-decision-record/SKILL.md
exports/openclaw/architecture-diagram/SKILL.md
exports/openclaw/archive-strategy/SKILL.md
exports/openclaw/assumption-bounty/SKILL.md
exports/openclaw/assumption-mapper/SKILL.md
exports/openclaw/async-update-format/SKILL.md
exports/openclaw/auto-repair-estimate-decoder/SKILL.md
exports/openclaw/autopilot-charter/SKILL.md
exports/openclaw/benefits-decoder/SKILL.md
exports/openclaw/bid-tender-review/SKILL.md
exports/openclaw/board-deck-narrative/SKILL.md
exports/openclaw/board-minutes/SKILL.md
exports/openclaw/board-pre-read/SKILL.md
exports/openclaw/bom-cost-review/SKILL.md
exports/openclaw/bookkeeping-categorization/SKILL.md
exports/openclaw/boolean-search-builder/SKILL.md
exports/openclaw/brag-doc/SKILL.md
exports/openclaw/brainstorming/SKILL.md
exports/openclaw/brief-builder/SKILL.md
exports/openclaw/briefing-note/SKILL.md
exports/openclaw/budget-builder/SKILL.md
exports/openclaw/budget-variance-analysis/SKILL.md
exports/openclaw/bug-diagnosis/SKILL.md
exports/openclaw/bug-report/SKILL.md

Metadata

Files
0
Version
471c606
Hash
811e543d
Indexed
2026-07-19 12:34

- 위키
Copyright © 2011-2026 iteam. Current version is 2.155.2. UTC+08:00, 2026-07-30 17:00
浙ICP备14020137号-1 $방문자$