"description": "Software project effort estimation assistant. Outputs three-point estimates (optimistic\/most-likely\/pessimistic values with confidence intervals), T-shirt sizes, or Function Point Analysis (FPA) counts. Triggered when users ask 'how long will this feature take,' need to assess project workload, perform PERT estimation, T-shirt sizing, FPA, sprint planning, or quote-based effort breakdowns."
}
Project Sizing Guide — Software Project Effort Estimation
Helps teams produce scientifically grounded effort estimates for software projects, based on three major methodologies: Three-Point Estimation (PERT), T-shirt Sizing, and Function Point Analysis (FPA). Outputs optimistic, most-likely, and pessimistic values along with risk intervals.
Quick Start
- User provides a requirements description → Agent identifies functional modules and breaks them into a Work Breakdown Structure (WBS)
- Select an estimation method → Choose the best-fit approach based on project stage and available information
- Estimate each item → Assign O/M/P (Optimistic / Most Likely / Pessimistic) values to every work package
- Aggregate and report → Generate an estimation report with risk analysis and confidence intervals
A calculation helper is available:
python3 scripts/estimate_calculator.py --method pert --tasks '[{"name":"User Login","O":2,"M":3,"P":8}]'
Method Selection Guide
| Scenario | Recommended Method | Rationale |
|---|---|---|
| Early feasibility study, rough budgeting | T-shirt Sizing | Little information available; quickly align on order of magnitude |
| Sprint planning, iteration estimation | Three-Point Estimation (PERT) | Good granularity with confidence intervals |
| Contract bidding, large-project RFPs | Function Point Analysis (FPA) | Most rigorous; industry-comparable |
| Team has historical data | PERT + historical calibration | Combines empirical correction with data |
Method 1: Three-Point Estimation (PERT)
Core Formulas
| Metric | Formula | Meaning |
|---|---|---|
| Expected Value E | (O + 4M + P) / 6 | Weighted average effort |
| Standard Deviation σ | (P − O) / 6 | Estimation uncertainty |
| Variance V | σ² | Used to aggregate across tasks |
| Project Total Expected | ΣE | Sum of individual expected values |
| Project Total Std Dev | √(ΣV) | Square root of summed variances |
Where:
- O (Optimistic): Shortest duration assuming everything goes smoothly
- M (Most Likely): Duration under normal circumstances
- P (Pessimistic): Longest duration when significant difficulties arise
Confidence Intervals
| Confidence Level | Interval | Use Case |
|---|---|---|
| 68.3% | E ± 1σ | Internal rough estimates |
| 90% | E ± 1.645σ | Project planning |
| 95% | E ± 2σ | External quotes |
| 99.7% | E ± 3σ | Contractual commitments |
Steps
- Build the WBS: Decompose requirements into the smallest independently estimable units (recommended ≤ 5 person-days each)
- Three-point estimation: For each work package, provide O / M / P values (use consistent units: person-hours or person-days)
- Calculate per-task expected value and standard deviation
- Aggregate project-level metrics: Total Expected = ΣE, Total Std Dev = √(Σσ²)
- Output confidence intervals: Choose a confidence level based on risk appetite
O/M/P Estimation Rules of Thumb
- O should not be less than 30% of M (overly optimistic suggests essential steps were overlooked)
- P should not exceed 5× M (overly pessimistic suggests unclear requirements that need clarification first)
- If O ≈ M ≈ P, the task is either extremely well-understood or the estimator hasn't seriously considered risks
- The P/O ratio (spread ratio) reflects uncertainty: < 2 = low risk, 2–4 = medium risk, > 4 = high risk
Method 2: T-shirt Sizing
Size Reference Table
| Size | Typical Range (person-days) | Typical Story Points | Suitable For |
|---|---|---|---|
| XS | 0.25 – 0.5 | 1 | Config changes, copy edits, simple bug fixes |
| S | 0.5 – 2 | 2 – 3 | Single-component development, simple API, minor UI tweaks |
| M | 2 – 5 | 5 – 8 | Complete feature module, moderately complex API |
| L | 5 – 15 | 13 – 21 | Cross-module features requiring integration |
| XL | 15 – 40 | 34 – 55 | Subsystem-level development requiring architecture design |
| XXL | 40+ | 89+ | Should be split across multiple iterations; not recommended as a single estimation unit |
Converting T-shirt Sizes to Three-Point Estimates
When more precise numbers are needed, T-shirt sizes can be converted to three-point estimates:
| Size | O (person-days) | M (person-days) | P (person-days) |
|---|---|---|---|
| XS | 0.25 | 0.5 | 1 |
| S | 0.5 | 1 | 2.5 |
| M | 2 | 3.5 | 7 |
| L | 5 | 10 | 20 |
| XL | 15 | 25 | 50 |
| XXL | 40 | 70 | 150 |
Steps
- Team alignment: Confirm what each size means (the table above is a reference; teams may customize)
- Independent assessment: Each person assigns a size independently to avoid anchoring bias
- Discuss discrepancies: When estimates differ by more than 2 sizes, a discussion is mandatory
- Reach consensus: Adopt the team consensus value
- Convert to numbers (optional): Use the table above to derive O/M/P values
Method 3: Function Point Analysis (FPA)
Five Function Component Types
| Component Type | Abbreviation | Definition | Example |
|---|---|---|---|
| Internal Logical File | ILF | Logical data group maintained by the application | Users table, Orders table |
| External Interface File | EIF | Data group referenced but not maintained by the application | Third-party exchange rate data |
| External Input | EI | Data processing entering the system from outside | Form submission, API POST |
| External Output | EO | Data generated and sent outside the system | Report generation, exports |
| External Inquiry | EQ | Simple data retrieval + display | List queries, detail pages |
Complexity Weight Matrix
| Component Type | Low | Medium | High |
|---|---|---|---|
| ILF | 7 | 10 | 15 |
| EIF | 5 | 7 | 10 |
| EI | 3 | 4 | 6 |
| EO | 4 | 5 | 7 |
| EQ | 3 | 4 | 6 |
Complexity Assessment Rules
ILF / EIF Complexity (based on DET – Data Element Types and RET – Record Element Types):
| DET 1-19 | DET 20-50 | DET 51+ | |
|---|---|---|---|
| RET 1 | Low | Low | Medium |
| RET 2-5 | Low | Medium | High |
| RET 6+ | Medium | High | High |
EI Complexity (based on DET and FTR – File Types Referenced):
| DET 1-4 | DET 5-15 | DET 16+ | |
|---|---|---|---|
| FTR 0-1 | Low | Low | Medium |
| FTR 2 | Low | Medium | High |
| FTR 3+ | Medium | High | High |
EO / EQ Complexity (based on DET and FTR):
| DET 1-5 | DET 6-19 | DET 20+ | |
|---|---|---|---|
| FTR 0-1 | Low | Low | Medium |
| FTR 2-3 | Low | Medium | High |
| FTR 4+ | Medium | High | High |
Converting Function Points to Effort
After calculating Unadjusted Function Points (UFP):
-
Calculate the Value Adjustment Factor (VAF) (optional; deprecated since IFPUG 4.3+ but still used by some teams)
- 14 General System Characteristics (GSC), each scored 0–5
- VAF = 0.65 + 0.01 × Σ(GSC)
- Adjusted Function Points AFP = UFP × VAF
-
Function points to person-hours
- Industry benchmark: 8–15 person-hours per function point (varies by language and team maturity)
Technology Stack Person-hours / FP Notes Low-code / Mature Frameworks 4 – 8 Many reusable components available Python / JS / Modern Web 8 – 12 Mainstream development productivity Java / C# Enterprise 10 – 15 Includes architecture and standards overhead Embedded / C / C++ 15 – 25 High debugging and testing cost Legacy System Maintenance 20 – 30 Comprehension and regression cost
Steps
- Identify function components: List all ILFs, EIFs, EIs, EOs, and EQs
- Assess complexity: Rate each component as Low / Medium / High
- Calculate UFP: Sum (count × weight) for all components
- Select conversion factor: Choose person-hours per FP based on technology stack
- Compute total effort: UFP × conversion factor
- Add buffer: A 15–30% management and risk buffer is recommended
Estimation Adjustment Factor Checklist
After completing the estimation, verify that the following factors have been accounted for:
Technical Factors
- Technology stack familiarity (Is the team experienced? If unfamiliar, add 30–50%)
- Technical debt (Poor legacy code quality? Add 20–40%)
- Third-party dependencies (Unstable APIs? Missing documentation? Add 10–30%)
- Performance / security requirements (Special non-functional requirements? Add 15–25%)
Team Factors
- Team size (Communication overhead increases significantly above 5 people; add ~5% per person)
- Personnel turnover risk (Key members may leave? Add 15–25%)
- Parallel projects (Team context-switching across multiple projects? Add 20–30%)
- Onboarding new members (New hires? Expect ~50% reduced efficiency for the first 2 weeks)
Process Factors
- Requirements stability (Requirements likely to change? Add 20–50%)
- Approval processes (Multiple layers of approval needed? Add 10–20%)
- Deployment complexity (Multi-environment, multi-region deployments? Add 10–15%)
- Compliance requirements (Audit or compliance processes? Add 15–30%)
Commonly Underestimated Work
- Code review: +10–15%
- Unit test authoring: +15–25%
- Integration / E2E testing: +10–20%
- Documentation: +5–15%
- Bug fixing and regression: +10–20%
- Environment setup and DevOps: +5–10%
- Meetings and communication: +10–15%
Estimation Output Template
After the Agent completes the estimation, it should produce output in the following format:
## Estimation Report: [Project / Feature Name]
### Estimation Method: [PERT / T-shirt / FPA]
### Work Package Breakdown
| # | Work Package | O (person-days) | M (person-days) | P (person-days) | E (person-days) | σ |
|---|-------------|-----------------|-----------------|-----------------|-----------------|---|
| 1 | xxx | x | x | x | x.x | x.x |
| 2 | xxx | x | x | x | x.x | x.x |
### Summary
- Total expected effort: X person-days
- Total standard deviation: X person-days
- 68% confidence interval: X – X person-days
- 90% confidence interval: X – X person-days
- 95% confidence interval: X – X person-days
### Adjustment Factors
- [Factors considered and adjustments applied]
### Final Recommendation
- For internal planning: X person-days (90% confidence)
- For external quotes: X person-days (95% confidence)
### Risk Alerts
- [Key risk items and mitigation suggestions]
Calculation Tool
The scripts/estimate_calculator.py script supports numerical calculations for all three estimation methods:
# Three-Point Estimation (PERT)
python3 scripts/estimate_calculator.py --method pert \
--tasks '[{"name":"Login Module","O":2,"M":3,"P":8},{"name":"Payment Module","O":5,"M":10,"P":20}]'
# T-shirt Size Conversion
python3 scripts/estimate_calculator.py --method tshirt \
--tasks '[{"name":"Login Module","size":"M"},{"name":"Payment Module","size":"L"}]'
# Function Point Analysis
python3 scripts/estimate_calculator.py --method fpa \
--components '[{"type":"ILF","complexity":"medium","count":3},{"type":"EI","complexity":"low","count":5}]' \
--hours-per-fp 10
References
- IFPUG (International Function Point Users Group) CPM 4.3.1
- PMI PMBOK Guide — 6th Edition, Section 6.4: Estimate Activity Durations
- Steve McConnell, Software Estimation: Demystifying the Black Art
- Mike Cohn, Agile Estimating and Planning