提供软件项目工作量估算的辅助技能,支持三点估算(PERT)、T恤尺码和函数点分析(FPA),输出置信区间和风险报告。

skills/project-sizing-guide/SKILL.md zebbern/claude-code-guide

Trigger Scenarios

询问功能开发时长 评估项目工作量 进行Sprint规划 报价分解

Install

npx skills add zebbern/claude-code-guide --skill project-sizing-guide -g -y
More Options

Use without installing

npx skills use zebbern/claude-code-guide@project-sizing-guide

指定 Agent (Claude Code)

npx skills add zebbern/claude-code-guide --skill project-sizing-guide -a claude-code -g -y

安装 repo 全部 skill

npx skills add zebbern/claude-code-guide --all -g -y

预览 repo 内 skill

npx skills add zebbern/claude-code-guide --list

SKILL.md

Frontmatter
{
    "name": "project-sizing-guide",
    "license": "MIT",
    "description": "Software project effort estimation assistant. Outputs three-point estimates (optimistic\/most-likely\/pessimistic values with confidence intervals), T-shirt sizes, or Function Point Analysis (FPA) counts. Triggered when users ask 'how long will this feature take,' need to assess project workload, perform PERT estimation, T-shirt sizing, FPA, sprint planning, or quote-based effort breakdowns."
}

Project Sizing Guide — Software Project Effort Estimation

Helps teams produce scientifically grounded effort estimates for software projects, based on three major methodologies: Three-Point Estimation (PERT), T-shirt Sizing, and Function Point Analysis (FPA). Outputs optimistic, most-likely, and pessimistic values along with risk intervals.

Quick Start

  1. User provides a requirements description → Agent identifies functional modules and breaks them into a Work Breakdown Structure (WBS)
  2. Select an estimation method → Choose the best-fit approach based on project stage and available information
  3. Estimate each item → Assign O/M/P (Optimistic / Most Likely / Pessimistic) values to every work package
  4. Aggregate and report → Generate an estimation report with risk analysis and confidence intervals

A calculation helper is available:

python3 scripts/estimate_calculator.py --method pert --tasks '[{"name":"User Login","O":2,"M":3,"P":8}]'

Method Selection Guide

Scenario Recommended Method Rationale
Early feasibility study, rough budgeting T-shirt Sizing Little information available; quickly align on order of magnitude
Sprint planning, iteration estimation Three-Point Estimation (PERT) Good granularity with confidence intervals
Contract bidding, large-project RFPs Function Point Analysis (FPA) Most rigorous; industry-comparable
Team has historical data PERT + historical calibration Combines empirical correction with data

Method 1: Three-Point Estimation (PERT)

Core Formulas

Metric Formula Meaning
Expected Value E (O + 4M + P) / 6 Weighted average effort
Standard Deviation σ (P − O) / 6 Estimation uncertainty
Variance V σ² Used to aggregate across tasks
Project Total Expected ΣE Sum of individual expected values
Project Total Std Dev √(ΣV) Square root of summed variances

Where:

  • O (Optimistic): Shortest duration assuming everything goes smoothly
  • M (Most Likely): Duration under normal circumstances
  • P (Pessimistic): Longest duration when significant difficulties arise

Confidence Intervals

Confidence Level Interval Use Case
68.3% E ± 1σ Internal rough estimates
90% E ± 1.645σ Project planning
95% E ± 2σ External quotes
99.7% E ± 3σ Contractual commitments

Steps

  1. Build the WBS: Decompose requirements into the smallest independently estimable units (recommended ≤ 5 person-days each)
  2. Three-point estimation: For each work package, provide O / M / P values (use consistent units: person-hours or person-days)
  3. Calculate per-task expected value and standard deviation
  4. Aggregate project-level metrics: Total Expected = ΣE, Total Std Dev = √(Σσ²)
  5. Output confidence intervals: Choose a confidence level based on risk appetite

O/M/P Estimation Rules of Thumb

  • O should not be less than 30% of M (overly optimistic suggests essential steps were overlooked)
  • P should not exceed 5× M (overly pessimistic suggests unclear requirements that need clarification first)
  • If O ≈ M ≈ P, the task is either extremely well-understood or the estimator hasn't seriously considered risks
  • The P/O ratio (spread ratio) reflects uncertainty: < 2 = low risk, 2–4 = medium risk, > 4 = high risk

Method 2: T-shirt Sizing

Size Reference Table

Size Typical Range (person-days) Typical Story Points Suitable For
XS 0.25 – 0.5 1 Config changes, copy edits, simple bug fixes
S 0.5 – 2 2 – 3 Single-component development, simple API, minor UI tweaks
M 2 – 5 5 – 8 Complete feature module, moderately complex API
L 5 – 15 13 – 21 Cross-module features requiring integration
XL 15 – 40 34 – 55 Subsystem-level development requiring architecture design
XXL 40+ 89+ Should be split across multiple iterations; not recommended as a single estimation unit

Converting T-shirt Sizes to Three-Point Estimates

When more precise numbers are needed, T-shirt sizes can be converted to three-point estimates:

Size O (person-days) M (person-days) P (person-days)
XS 0.25 0.5 1
S 0.5 1 2.5
M 2 3.5 7
L 5 10 20
XL 15 25 50
XXL 40 70 150

Steps

  1. Team alignment: Confirm what each size means (the table above is a reference; teams may customize)
  2. Independent assessment: Each person assigns a size independently to avoid anchoring bias
  3. Discuss discrepancies: When estimates differ by more than 2 sizes, a discussion is mandatory
  4. Reach consensus: Adopt the team consensus value
  5. Convert to numbers (optional): Use the table above to derive O/M/P values

Method 3: Function Point Analysis (FPA)

Five Function Component Types

Component Type Abbreviation Definition Example
Internal Logical File ILF Logical data group maintained by the application Users table, Orders table
External Interface File EIF Data group referenced but not maintained by the application Third-party exchange rate data
External Input EI Data processing entering the system from outside Form submission, API POST
External Output EO Data generated and sent outside the system Report generation, exports
External Inquiry EQ Simple data retrieval + display List queries, detail pages

Complexity Weight Matrix

Component Type Low Medium High
ILF 7 10 15
EIF 5 7 10
EI 3 4 6
EO 4 5 7
EQ 3 4 6

Complexity Assessment Rules

ILF / EIF Complexity (based on DET – Data Element Types and RET – Record Element Types):

DET 1-19 DET 20-50 DET 51+
RET 1 Low Low Medium
RET 2-5 Low Medium High
RET 6+ Medium High High

EI Complexity (based on DET and FTR – File Types Referenced):

DET 1-4 DET 5-15 DET 16+
FTR 0-1 Low Low Medium
FTR 2 Low Medium High
FTR 3+ Medium High High

EO / EQ Complexity (based on DET and FTR):

DET 1-5 DET 6-19 DET 20+
FTR 0-1 Low Low Medium
FTR 2-3 Low Medium High
FTR 4+ Medium High High

Converting Function Points to Effort

After calculating Unadjusted Function Points (UFP):

  1. Calculate the Value Adjustment Factor (VAF) (optional; deprecated since IFPUG 4.3+ but still used by some teams)

    • 14 General System Characteristics (GSC), each scored 0–5
    • VAF = 0.65 + 0.01 × Σ(GSC)
    • Adjusted Function Points AFP = UFP × VAF
  2. Function points to person-hours

    • Industry benchmark: 8–15 person-hours per function point (varies by language and team maturity)
    Technology Stack Person-hours / FP Notes
    Low-code / Mature Frameworks 4 – 8 Many reusable components available
    Python / JS / Modern Web 8 – 12 Mainstream development productivity
    Java / C# Enterprise 10 – 15 Includes architecture and standards overhead
    Embedded / C / C++ 15 – 25 High debugging and testing cost
    Legacy System Maintenance 20 – 30 Comprehension and regression cost

Steps

  1. Identify function components: List all ILFs, EIFs, EIs, EOs, and EQs
  2. Assess complexity: Rate each component as Low / Medium / High
  3. Calculate UFP: Sum (count × weight) for all components
  4. Select conversion factor: Choose person-hours per FP based on technology stack
  5. Compute total effort: UFP × conversion factor
  6. Add buffer: A 15–30% management and risk buffer is recommended

Estimation Adjustment Factor Checklist

After completing the estimation, verify that the following factors have been accounted for:

Technical Factors

  • Technology stack familiarity (Is the team experienced? If unfamiliar, add 30–50%)
  • Technical debt (Poor legacy code quality? Add 20–40%)
  • Third-party dependencies (Unstable APIs? Missing documentation? Add 10–30%)
  • Performance / security requirements (Special non-functional requirements? Add 15–25%)

Team Factors

  • Team size (Communication overhead increases significantly above 5 people; add ~5% per person)
  • Personnel turnover risk (Key members may leave? Add 15–25%)
  • Parallel projects (Team context-switching across multiple projects? Add 20–30%)
  • Onboarding new members (New hires? Expect ~50% reduced efficiency for the first 2 weeks)

Process Factors

  • Requirements stability (Requirements likely to change? Add 20–50%)
  • Approval processes (Multiple layers of approval needed? Add 10–20%)
  • Deployment complexity (Multi-environment, multi-region deployments? Add 10–15%)
  • Compliance requirements (Audit or compliance processes? Add 15–30%)

Commonly Underestimated Work

  • Code review: +10–15%
  • Unit test authoring: +15–25%
  • Integration / E2E testing: +10–20%
  • Documentation: +5–15%
  • Bug fixing and regression: +10–20%
  • Environment setup and DevOps: +5–10%
  • Meetings and communication: +10–15%

Estimation Output Template

After the Agent completes the estimation, it should produce output in the following format:

## Estimation Report: [Project / Feature Name]

### Estimation Method: [PERT / T-shirt / FPA]

### Work Package Breakdown

| # | Work Package | O (person-days) | M (person-days) | P (person-days) | E (person-days) | σ |
|---|-------------|-----------------|-----------------|-----------------|-----------------|---|
| 1 | xxx         | x               | x               | x               | x.x             | x.x |
| 2 | xxx         | x               | x               | x               | x.x             | x.x |

### Summary

- Total expected effort: X person-days
- Total standard deviation: X person-days
- 68% confidence interval: X – X person-days
- 90% confidence interval: X – X person-days
- 95% confidence interval: X – X person-days

### Adjustment Factors
- [Factors considered and adjustments applied]

### Final Recommendation
- For internal planning: X person-days (90% confidence)
- For external quotes: X person-days (95% confidence)

### Risk Alerts
- [Key risk items and mitigation suggestions]

Calculation Tool

The scripts/estimate_calculator.py script supports numerical calculations for all three estimation methods:

# Three-Point Estimation (PERT)
python3 scripts/estimate_calculator.py --method pert \
  --tasks '[{"name":"Login Module","O":2,"M":3,"P":8},{"name":"Payment Module","O":5,"M":10,"P":20}]'

# T-shirt Size Conversion
python3 scripts/estimate_calculator.py --method tshirt \
  --tasks '[{"name":"Login Module","size":"M"},{"name":"Payment Module","size":"L"}]'

# Function Point Analysis
python3 scripts/estimate_calculator.py --method fpa \
  --components '[{"type":"ILF","complexity":"medium","count":3},{"type":"EI","complexity":"low","count":5}]' \
  --hours-per-fp 10

References

  • IFPUG (International Function Point Users Group) CPM 4.3.1
  • PMI PMBOK Guide — 6th Edition, Section 6.4: Estimate Activity Durations
  • Steve McConnell, Software Estimation: Demystifying the Black Art
  • Mike Cohn, Agile Estimating and Planning

Version History

  • 1ed99ef Current 2026-07-25 05:53

Same Skill Collection

skills/academic-paper-reviewer/SKILL.md
skills/active-directory-attacks/SKILL.md
skills/api-fuzzing-bug-bounty/SKILL.md
skills/api-shape-explorer/SKILL.md
skills/audit-flow/SKILL.md
skills/authentication-patterns/SKILL.md
skills/aws-penetration-testing/SKILL.md
skills/broken-authentication/SKILL.md
skills/burp-suite-testing/SKILL.md
skills/caching/SKILL.md
skills/chart-image/SKILL.md
skills/cloud-penetration-testing/SKILL.md
skills/code-documenter/SKILL.md
skills/code-to-diagram/SKILL.md
skills/composition-patterns/SKILL.md
skills/cross-examine/SKILL.md
skills/cv-tailor/SKILL.md
skills/data-viz-renderer/SKILL.md
skills/database-optimizer/SKILL.md
skills/database-scout/SKILL.md
skills/dataset-quality-audit/SKILL.md
skills/deep-module-refactor/SKILL.md
skills/design-system-builder/SKILL.md
skills/dev-guide-generator/SKILL.md
skills/ethical-hacking-methodology/SKILL.md
skills/file-path-traversal/SKILL.md
skills/html-injection-testing/SKILL.md
skills/http-load-profiler/SKILL.md
skills/idor-testing/SKILL.md
skills/linux-privilege-escalation/SKILL.md
skills/linux-shell-scripting/SKILL.md
skills/localization-toolkit/SKILL.md
skills/log-error-digest/SKILL.md
skills/metasploit-framework/SKILL.md
skills/network-101/SKILL.md
skills/nextjs-developer/SKILL.md
skills/pdf/SKILL.md
skills/pentest-checklist/SKILL.md
skills/pentest-commands/SKILL.md
skills/pipeline-blueprint/SKILL.md
skills/playwright/ci/SKILL.md
skills/playwright/core/SKILL.md
skills/playwright/migration/SKILL.md
skills/playwright/playwright-cli/SKILL.md
skills/playwright/pom/SKILL.md
skills/playwright/SKILL.md
skills/privilege-escalation-methods/SKILL.md
skills/r2-upload/SKILL.md
skills/r3f-animation/SKILL.md

Metadata

Files
0
Version